Works Minister David Umahi has threatened to ordered the arrest of the managing director of Hartland Nigeria Limited after accusing the company of failing to deliver an 11-kilometre section of the Benin–Onitsha Expressway despite receiving about ₦14 billion for the project.
Umahi issued the threat during an inspection of road infrastructure along the Agbor–Asaba–Onitsha corridor in Delta State, where he expressed anger over the level of work on the affected section. He said the contractor had completed only about 40 per cent of the job.
The minister said he had previously contacted Hartland’s managing director to discuss the company’s return to the site, but the contractor had not met the expectations of the ministry.
He then made clear that he intended to take action against the company’s head.
“I’ve called the MD to discuss their return to the site. I am going to look for him and have him arrested. I’m going to arrest him.”
Umahi subsequently directed the ministry’s controller to locate the managing director and carry out the arrest. He also ordered officials to begin steps aimed at recovering the money already paid to Hartland.
The minister said the payment was tied to an agreement for Hartland to complete the entire stretch from Summit Junction to the Head Bridge. The contract also covered channelisation and hydraulic structures along the route.
Umahi questioned the level of work achieved after the funds were released, saying the contractor had delivered only about 40 per cent of what had been agreed.
“Today, they have only completed about 40 per cent of what was agreed upon.”
He ordered the relevant departments of the Federal Ministry of Works to activate the advance payment guarantee and begin discussions with the banks involved in recovering the money.
The minister also directed an audit of Hartland’s payment records and certificates for its projects with the ministry. He said the contractor would face sanctions if the review found it wanting.
Beyond the dispute with Hartland, Umahi ordered immediate attention to the approach to the Head Bridge, directing that both sides be filled without delay.
The confrontation with Hartland came during a wider inspection of federal road and bridge infrastructure in the area. Umahi also raised concerns over the removal of bolts, steel members and expansion joints from the Second Niger Bridge and ordered repairs and stronger surveillance.
The minister directed that solar-powered lights and closed-circuit television cameras be installed around the bridge, with designated ministry and security officials given access to the surveillance system. He also ordered remedial work on erosion around the bridge.
For Hartland, the immediate consequences of Umahi’s directive are the proposed arrest of its managing director, efforts to recover funds paid under the contract and a review of the company’s records. The minister’s allegations remain subject to the outcome of those official processes.